QUESTION NO: 1
A customer is deploying a Multimedia Communication Server
(MCS) 5100 Rls. 4.0 four-server system with all users
being assigned IP Phone 2004 telephones. The customer
would like to ensure that all users are able to determine
the current status of other users on the MCS 5100 system.
How is this service provided by the SIP Presence Module
in an MCS 5100 system?
A. The SIP Presence Module running on the System Manager
will provide this information.
B. The SIP Presence Module running on the Session Manager
will provide this information.
C. The SIP Presence Module running on the IP Client
Manager will provide this information.
D. The MCS 5100 system will have to be upgraded to an
eight-server system to support the SIP Presence Module.
Answer: B
QUESTION NO: 2
Where is the Unified Network IP Stimulus (UNIStim) protocol
used in a Multimedia Communication Server (MCS) 5100
Rls. 4.0 network?
A. on ISDN PRI connections to the PSTN
B. between IP Phones and the IP Client Manager (IPCM)
C. between the Provisioning Client and an external SIP
Gateway
D. between the System Management Console and the Session
Manager
Answer: B
QUESTION NO: 3
A service provider wants to use a console connection
to configure a four-server Multimedia Communication
Server (MCS) 5100 Rls. 4.0 system from a common platform.
What hardware is required?
A. a Layer 2 switch
B. a Layer 3 switch
C. a Terminal Server
D. a System Management Console PC
Answer: D
QUESTION NO: 4
The technician is viewing a command typed from a PuTTY
terminal that verifies the IP addressing for the System/Accounting
Manager. If the interface eth0 is not UP (it is unavailable),
to which interface would the machine logically attach
itself?
A. lo0
B. eth1
C. dmfe0
D. dmfe0:2
Answer: B
QUESTION NO: 5
A support engineer is preparing to install a Multimedia
Communication Server (MCS) 5100 Rls. 4.0 system. The
MCS 5100 servers have all been physically installed
and cabled to the In-Reach Terminal Server. Which information
should you configure on the In-Reach Terminal Server
to allow access to the MCS 5100 servers through it?
A. Define the IP address for each MCS 5100 server.
B. Define the IP address for the Management Console
PC.
C. Define the port speed for each MCS 5100 server connection.
D. Define the IP Address port number to which the MCS
5100 server is connected.
Answer: C
QUESTION NO: 6
An administrator is in the process of installing the
Multimedia Communication Server (MCS) 5100 Rls. 4.0
software. The Management Console Graphical User Interface
(GUI) has successfully launched. What is the next step
in the installation process for a four-server system?
A. Deploy the Session Manager.
B. Deploy the Accounting Manager.
C. Deploy the Provisioning Manager.
D. Verify the deployment of the System Manager.
Answer: B
QUESTION NO: 7
During the deployment of a four-server Multimedia Communication
Server (MCS) 5100 Rls. 4.0 system, the System Management
Console application has been launched. Before uploading
the license key, which components are deployed and running
by default?
A. the System Managerand a Database instance
B. the Session Managerand the Accounting Manager
C. the System Managerand the Provisioning Manager
D. the Database Manager and the Accounting Manager
Answer: A
QUESTION NO: 8
A support engineer is in the process of executing the
Multimedia Communication Server (MCS) 5100 Rls. 4.0
software load in a four-server installation. The ./mcpInstall.pl
script is successfully installed. What is the next step
in the software installation process?
A. Add and configure the Accounting Module.
B. Install and launch the IPCM on the System Manager.
C. Deploy the initial database load on the Database
Manager.
D. Launch the Management Console on the management PC.
Answer: D