Question:
1
You are deploying new GbE2 Interconnect Switches,
both still configured with factory default settings.
You need to reconfigure the setting to match your
network infrastructure. You connect to switch A through
the external uplink port 19, but your attempt to activate
the GbE2 Remote Management IP interface fails. What
is the cause of the failure?
A. the crosslinks are enabled by default, causing
infinite loops between the interconnect switches
B. the GbE2 Remote Management IP interface is disabled
by default
C. the spanning tree protocol is disabled for VLAN
1
D. the uplink port 19 is not added to the default
VLAN 1
Answer: B
Question:
2
How many server bays are available in
A. 8
B. 12
C. 16
D. 20
Answer: A
Question:
3
You have an original server blade enclosure
fu provide power redundancy to those blade
A. one fully populated power enclosure; server
B. two fully populated power enclosures; server blade
enclosure side A connected to side A of
C. one fully populated power enclosure; server
D. two fully populated power enclosures; server blade
enclosure side A connected to side A of power enclosure
1; server blade enclosure side B connected to side
B of power enclosure 2
Answer: C
Question:
4
Which technology is required to eliminate
loops in bridged networks?
A. Identity-Based Networ
B. Port trunking
C. Spanning Tree Protocol (STP)
D. VLAN tagging
Answer: C
Question:
5
Which software packages make up the HP ProLiant
Essentials Rapid Deployment Pack? Select THREE.
A. Altiris Deployment Server
B. Automation Manager
C. HP BladeSystem Integrated Management.
D. Integrated Lights-Out Advanced
E. ProLiant Integration Module
F. SmartStart Scripting Toolkit
Answer: A, E, F
Question:
6
What is the correct choice of HP management
software to provide these capabilities?
- A common enterprise platform for hardware and service
level management
- Multi-vendor systems management
- In-depth hardware lifecycle management
- System software version control
- Hardware status and fault management
- HP BladeSystem support
A. HP OpenView Operations for Windows
B. HP OpenView Operations for Windows integrated with
HP OpenView Network Node Manager
C. HP Systems Insight Manager
D. HP Systems Insight Manager integrated with HP OpenView
Operations for Windows
Answer: D
Question:
7
What is the maximum number of ProLiant BL30p
server blades that fit into a 42U rack with redundant
power configuration?
A. 72
B. 80
C. 92
D. 96
Answer: B
Question:
8
Which hardware information file must you
use in the RDP 1.60 deployment job to have ProLiant
BL20p G2/G3 server blades boot Red Hat Enterprise
Linux AS 3 from SAN?
A. bl20p-a.ini
B. bl20p-h.ini
C. linux-h.ini
D. pl-bfs.ini
Answer: D